Building diary Multifunctional building

Preview Multifunctional building

With this construction diary, we want to keep all interested parties up to date with the progress of our new multifunctional building. On the grounds of our stadium on Rochlitzer Straße, a multifunctional building with a large sanitary wing, changing rooms and a 180 square meter gym will be built. Of the approximately 1.1 million euros in construction costs, the Free State of Saxony supports 50 %, the district of Mittelsachsen 75,000 euros and 250,000 euros the city of Lunzenau. The rest is to be paid by the association as own contribution. This will require around 4,500 hours of work by our association members. The project is scheduled to be completed in summer 2022.

Supporters of the project

Logo Free State of Saxony

This construction project is co-financed by tax resources on the basis of the budget decided by the Saxon Parliament.


Logo District of Central Saxony

This construction project is co-financed by budget appropriations on the basis of the budget decided by the district council of the district of Mittelsachsen.


This construction project is co-financed by budget appropriations on the basis of the budget decided by the Lunzenau City Council.



to KW25/2023

The last construction works have now been completed. The street in front of the multifunctional building and the new spectator entrance for events was paved, a small standing place grandstand was built. Furthermore, the ball catching facility was completed and the beach volleyball court was filled with sand.

KW43/2022

A lot has happened with us in the last few weeks. So we were able to embellish the main and secondary entrance with a foil and all rooms in the multifunctional building were signposted. With a TV in the entrance hall, we will give our sponsors another opportunity to present themselves in the future and we can also show the teams in which cabin they have to go. Now we have also furnished all the changing rooms and they are now ready for training and competition operations. We have also been able to conserve our material space great and are very enthusiastic about the large storage space.

CW33/2022

This is where the ball net system is built to protect the new multifunctional building and its windows from shots.

CW28/2022

The paving work continued and the stairs to the later office of the SVFL were installed.

KW27/2022

Here the outdoor areas were further paved and by the helpers from our association the sand was stopped for the first time.

KW25/2022

KW24/2022

KW22/2022

KW21/2022

CW20/2022

KW19/2000

CW18/2022

Here, the exterior facades of the multifunctional building could be completely painted, so that the work is now carried on exclusively inside.

CW17/2022

This week, the wall of the gymnasium on Rochlitzer Straße was plastered for the second time, the washroom of the referee's cabin was tiled and the hall floor, as well as the impact protection was laid out.

CW16/2022

The last wall above the social wing was plastered and the felt plaster was applied in the social wing.

KW15/2022

This week, all the exterior walls of the entire building were plastered and work in the gym could continue.

CW14/2022

The tile work in the sanitary area of the home team has continued and is close to completion.

CW13/2022

In the 13th During the calendar week, the work in the building could be continued by laying the first tiles in the shower cubicle of the home team and installing the first door frames.

CW12/2022

The screed gets its necessary rest to dry.

KW11/2022

This week, the screed was let into the building.

KW10/2022

In the 10th. The underfloor heating was designed for the calendar week.

KW09/2022

Preparations for underfloor heating continued and flooring is now also being prepared in the gymnasium.

KW08/2022

This week, the interior plastering work was completed and underfloor heating started to be prepared. Furthermore, the relaxation pool for the home cabins was built.

CW07/2022

The drywall panels are now almost completely installed in the building. The interior plastering work in the social wing continues to be carried out. Furthermore, a foil was glued to the gable windows of the gymnasium.

CW06/2022

This week, the plastering work in the later guest cabins was almost completed and the drywall work continued in the main corridor.

CW05/2022

The connection between the clubhouse and the multifunctional building is close to completion, the heating pipes were insulated and the doors in the gymnasium were used.

KW04/2022

On the outside of the social wing, the cleaning work and the canal connections between Vereinsheim and multifunctional buildings continued. Furthermore, the scaffolding in the gymnasium was dismantled and the drywall work continued.

CW03/2022

The drywall works in the social wing are half completed. The electrical and plumbing work continued.

KW02/2022

In the second calendar week, the devices for the showers were milled out, as well as the heating room equipped with the necessary equipment. Furthermore, the ceiling in the home cabin was covered with plasterboards

KW01/2022

This week, the cable ducts were milled out, the heaters in the gym were connected to each other, all toilet directions were installed and the first heating pipes in the social wing were also installed.

KW 50/2021

This week, the heating system was installed and installed under the roof of the hall. The second layer of plaster was applied in the gym.

KW 49/2021 Interior plastering in the gym

The picture shows one of the walls of the gym, which was plastered this week.

KW 48/2021 Insulation work and exterior plastering

This week, the insulation was completed under the roof of the social wing and the foil was attached. In addition, plastering work continued on the outside and in the gymnasium.

KW 47/2021 Exterior plastering and interior work

The first pages of the multifunctional building were cleaned for the first time. In addition, the insulation work began under the roof of the social wing. Welding membranes were laid on the floors in the social wing.

KW 46/2021 Roof work completed

The roof has been completed and the gutter has been installed at the front of the building.

KW 45/2021 Now it's time for the windows

The windows, as well as the first door on the social wing are installed. The slate panels on the front of the roof were installed.

KW 44/2021 The roof is dense

In week 44, the roof of the social wing of the Fultifunction building was completed.

KW 43/2021 The roof beams are laid

The roof beams have all been mounted and now the roof can be closed.

KW 42/2021 The social wing continues

The social wing has reached its final height and can now be prepared for roof work.

KW 41/2021 The windows are fully installed.

After all windows were installed in the gymnasium, the scaffolding on the facade of the gymnasium was dismantled and rebuilt on the facade of the social wing. Due to the progressive masonry work, more and more spaces in the social wing can be recognized.

KW 40/2021 The roof is tight!

The work on the hall roof has been completed. The first fenests are delivered and already installed. Work on the social wing continues.

KW 39/2021 Topping-out ceremony for the multifunctional building

Work on the hall roof and social wing continued in KW39. There was also a report in KabelJournal Chemnitzer-Land.
https://www.kabeljournal-chemnitzer-land.de/index.php?option=com_content&task=view&id=4986&Itemid=1

KW 38/2021 The social wing is starting to grow

The hall roof now also receives the intended coating and sealing.

KW 37/2021 The hall roof is closed

At the same time, work on the social wing is being driven forward.

KW 36/2021 Roof assembly is progressing

KW 35/2021 It smells of color

The wooden beams and boards were painted by helpers from the association.

KW 34/2021 It goes on with the roof

KW 33/2021 The roof construction is installed

KW 32/2021 Preparations for the roof

KW 31/2021 The social wing is starting to grow

KW 30/2021 We are gaining in height

The future building is taking on more and more shape and the formwork for the windows has been tackled.

KW 29/2021 The building is growing...

In the KW29, the building has continued to grow and the hall soon reached its maximum height.

KW 28/2021 1. Floor ceiling cast

In this calendar week, the first floor ceiling has already been cast and soon the next floor will be visible.

KW 26/27/2021 The building is growing

In the last two weeks, the building is growing more and more and the gym can already be seen well. Furthermore, the connections to gas, water and electricity were laid.

KW 25/2021 Laying of the foundation stone

With the laying of the foundation stone on Saturday (26.06.21), another important step in our project was achieved. A lot of work, effort and sweat will still be needed to achieve the goal.

A ‘time capsule’ with some up-to-date documents was also cemented into the base plate. Perhaps our descendants can find and evaluate them.

KW 24/2021 The first stones...

Last week, the first stones for the building were delivered and set.

Other parts of the drainage system were also advanced.

KW 23/2021 Casting of the base plate

This week we have reached a major milestone by casting the base plate.

KW 22/2021 Completion of foundation work

The last foundations have been set and the preparations for pouring the base plate have begun.

With the help of many members of the association, the foundation work was completed last weekend and the soil can soon be poured.

KW 21/2021 Floor plate in sight

This week, supply lines and drain pipes were laid, as well as the preparation for the floor plate was advanced.

KW 20/2021 Foundations soon ready

The foundations of the social building are nehezu finished and the preparations for the floor plate are progressing.


KW 19/2021 Foundation work is progressing

Last week, the foundations were set and worked on and the first preparations for the floor slab were made.

KW 18/2021 The foundation is growing...

Also this week the work on the foundation of the building could be continued.

KW 17/2021 Foundation work continued

This week, more materials were delivered and prepared for the construction of the foundations. The reinforcing irons were assembled on site and brought into the foundation shafts.

The concreting work could then begin.

KW 16/2021 Preparation of foundations

This week, the floor area for the building was straightened and the first foundations were prepared.

KW 15/2021 Earthworks

This week, the earthworks of the cisterns continued.

KW 13-14/2021 Connection cistern tank

From 01.-09.04.2021, the pipe connections between the tanks were made.

KW 13/2021 Excavation of the cistern pit

To drain the slope, the pit for the cistern was completed on 29 and 30 March 2021.

Without much delay, the cistern was placed in the excavation pit on 31.03.2021.

KW 12/2021 Groundbreaking ceremony for the multifunctional building

It's time! On 27.03.2021, the symbolic groundbreaking ceremony took place on the site. This was, of course, back in the Local media Appreciated.

KW 11/2021 Construction of construction road

In March, 19.03.2021, the access road for construction vehicles was laid out.

KW 07/2021 Tree felling

On 17 February 2021, further space was created for the project through tree felling.

KW 51/2020 Contract award to various trades

After further planning tasks, the first contracts were awarded to various trades on 14.12.2020.

Without much delay, the old workshop building was dismantled on 16.12.2020.

KW 48/2020 Handover of grant notice

Now we can start – the new construction of our multifunctional building has been sealed – our sports club Fortschritt Lunzenau has finally received the grant decision! This was also reflected in the Regional media reported. There was also, of course, an comprehensive contribution on our association side.